Khusall Garh Bridge construction agreement

Source Daily Mashriq

An agreement has been finalised between NHA, OGDC and MOL for the construction of bridge at Khuskhal Garh Kohat. According to details the agreement will be signed on 14th October.The agreement inter alia says that to transport the Oil and gas found in Karak and Sakirdara area to Attock refinery the Khashall Garh is the best route so it should be immediately built. The funding should be 50 percent financed by NHA while remaining 50 percent should be shared by OGDC and MOL equally. The brigde should be prepared in 27 months and work on it will be started in the mid of November 2010. The cost on the bridge is about 1.4 billion rupees.